Each section has a short video (no sound) and the same steps with screenshots below it. The screenshots use an example plant, Example Wheels Ltd, whose CNC Cell 2 reworks too many 18-inch SUV wheels.
Write the problem in the fish head, then add every possible cause under the branch it belongs to.
Start with the problem statement in the fish head: what is wrong, where, since when and how much.
Click + on a branch to add a cause under it, and describe the cause briefly.
Add every cause the team can think of. A branch can hold several causes.
The six branches suit manufacturing. Click a branch name to rename it, or × beside it to remove it, to match your own template.
Each stakeholder scores every cause; the highest totals are the causes to check first.
Click "Move Causes to Table". Each stakeholder scores every cause from 1 (low priority) to 10 (high priority); the causes with the highest total become the top 5.
Type each stakeholder's name in a column heading, add details where they help, and enter the scores.
Click "Calculate Top 5 Causes". The table is sorted by total and the top causes are highlighted. Causes that tie at the cutoff are all highlighted, so there can be more than 5.
The top causes are highlighted on the diagram too.
Need more voices? "Add Stakeholder Column" adds another column; enter its scores and calculate the top 5 again.
A high score shows where to look first, not what the root cause is. The 5 Whys tool checks each top cause with evidence.
Under the table, "Drill into this with 5 Whys" opens the 5 Whys tool in a new tab with the problem and that cause filled in.
The Excel keeps the prioritization table and a picture of the diagram. Nothing is kept on the page after you leave it.
Click "Export Excel" to download the table, with the scoring rule above it and the diagram embedded, as one Excel file.